Latest news on MECF

Mid April 2017

Preparation of the site is underway for construction to commence.

Early April 2017

The contract is signed with Leighs Construction Limited for the construction of the new accommodation block (Building C).

February 2017

Leighs Construction Limited selected as the Preferred Tenderer to take forward into contract negotiations.

January 2017

Responses received to the RFT from Leighs Construction Limited and Fletcher Construction.

September 2016

The Request for Tender (RFT) was released on GETs for the procurement of the new accommodation block.